Reference projects

Highlights from over 100 completed Fast Beam projects

Fast Beam configuration

8 hangers, 7 platforms

Installation time

Rotation

Installation crew

3 people

Deck length

120 m

Project duration

3 months

Scotland, UK

Friarton

Fast Beam configuration

2 hangers, 1 platform

Installation time

30 minutes

Installation crew

2 people

Deck length

3 km

Project duration

24 months

Birmingham, UK

M1 Oldbury

Fast Beam configuration

42 hangers, 41 platforms

Installation time

10 hours

Installation crew

6 people

Deck length

200 m

Project duration

6 months

Kurikka, Finland

Paulanharju bridge

Fast Beam configuration

13 hangers, 12 platforms

Installation time

2 days

Installation crew

4 people

Deck length

60 m

Project duration

2 months

Dragsvik, Norway

Dragsvik harbor

Fast Beam configuration

33 hangers, 32 platforms

Installation time

Rotation

Installation crew

8 people

Deck length

360 m

Project duration

9 months

Ramel, France

Ramel valley

Fast Beam configuration

10 hangers, 9 platforms

Installation time

6 hours

Installation crew

3 people

Deck length

47 m

Project duration

3 months

Sysmä, Finland

Sysmänjoensilta

Fast Beam configuration

33 hangers, 32 platforms

Installation time

Rotation

Installation crew

4 people

Deck length

1050 m

Project duration

12 months

Kungälv, Sweden

Göteborg Kungälv

Fast Beam configuration

33 hangers, 32 platforms

Installation time

Rotation

Installation crew

6 people

Deck length

480 m

Project duration

6 months

Katfoss, Norway

Vickersund / Katfoss

Fast Beam configuration

23 hangers, 22 platforms

Installation time

10 hours

Installation crew

3 people

Deck length

118 m

Project duration

11 weeks

Mäntsälä, Finland

Marjala intersection bridge

Fast Beam configuration

13 hangers, 12 platforms

Installation time

5 hours

Installation crew

3 people

Deck length

68 m

Project duration

5 weeks

Karhula, Finland

Karhula twin bridges

Fast Beam configuration

15 hangers, 14 platforms

Installation time

8.5 hours

Installation crew

4 people

Deck length

76 m

Project duration

10 weeks

Umeå, Sweden

Boxby

Fast Beam configuration

6 hangers, 5 platforms

Installation time

3 hours

Installation crew

3 people

Deck length

27 m

Project duration

5 weeks

Umeå, Sweden

Ladyån